After two years, Buffalo Speedway reconstruction project could be completed by end of April

  • 📰 HoustonChron
  • ⏱ Reading Time:
  • 38 sec. here
  • 2 min. at publisher
  • 📊 Quality Score:
  • News: 19%
  • Publisher: 51%

Education Education Headlines News

Almost two years since the project broke ground, the city of West University Place...

A view looking south at the intersection of Bissonette and Buffalo Speedway of the signage, cones and barrels for the continuing construction along Buffalo Speedway Thursday, Jan. 26, 2023 in Houston, TX., West University Place officials anticipate drainage and mobility improvements on Buffalo Speedway to be completed by the end of April.

The $35 million Buffalo Speedway Reconstruction Project is replacing underground drainage pipes that were in place since the 1940s with large box culverts from Bissonnet to the West U's outfall at Poor Farm Ditch. The project was split into two stages and was overseen by the Texas Department of Transportation and West U. The new box culverts should decrease the likelihood of flooding during major rain events, TxDOT reports.

Buffalo Speedway has experienced traffic congestion, closed lanes and downed street lights since the project began. The city released a notice on March 29, saying that they are aware of the streetlights that are currently out on Buffalo Speedway and are working with CenterPoint Energy to get them fixed.

 

Thank you for your comment. Your comment will be published after being reviewed.
Please try again later.
We have summarized this news so that you can read it quickly. If you are interested in the news, you can read the full text here. Read more:

 /  🏆 609. in EDUCATÄ°ON

Education Education Latest News, Education Education Headlines